Official US Government Icon

Official websites use .gov
A .gov website belongs to an official government organization in the United States.

Secure Site Icon

Secure .gov websites use HTTPS
A lock ( ) or https:// means you’ve safely connected to the .gov website. Share sensitive information only on official, secure websites.

(TX) US 82 (FM 1197 - SH 175)

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.

In Progress icon

ENVIRONMENTAL REVIEW AND PERMITTING STATUS
IN PROGRESS

ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
SUBJECT TO CHANGE

2 out of 3

ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

Surface Transportation icon

SECTOR
Surface Transportation

CATEGORY
DOT Projects

Texas icon

LEAD AGENCY
Texas

Other Agencies with Actions or Authorizations:

Department of the Army icon

Department of the Army, US Army Corps of Engineers - Regulatory

Description:

The proposed US 82 project would upgrade the existing two-lane undivided highway to a fourlane
rural divided highway. In the areas where proposed US 82 would be divided by a
depressed grassy median, the typical section would consist of four 12-foot wide lanes (two in
each direction) with 4-foot wide inside shoulders and 10-foot wide outside shoulders divided by
a 68-foot wide depressed grassy median. In the areas where proposed US 82 would be divided
by a center left turn lane, the typical section would consist of four 12-foot wide lanes (two in
each direction) with 10-foot wide outside shoulders divided by a 16-foot wide center left turn
lane. The construction length of the project would be approximately 26.6 miles. Construction
would include some minor realignments of intersecting roads which would provide safer, more
convenient intersections. Median crossovers would be provided to accommodate residents and
businesses.

Permitting Timetable

The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.

  • For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Loading ...
Overall Project Timetable
 
STATUS
Schedule
Extension or Delay
Ahead of Schedule
Paused
No End Date
Planned

Action Information

For additional information, please select an Action from the Permitting Timetable above.

  • Action:  
  • Responsible Agency:  
  • Bureau:  
  • Action Status:  
  • SHPO:  
  • Action Identifier:  
  • Action Outcome:  
Milestone Original Target Date Current Target Date Milestone Complete