Brooks Bridge Replacement Study

PROJECT WEBSITE: Brooks Bridge Replacement Study

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.

In Progress icon

ENVIRONMENTAL REVIEW AND PERMITTING STATUS
IN PROGRESS

ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
SUBJECT TO CHANGE

4 out of 7

ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

Surface Transportation icon

SECTOR
Surface Transportation

CATEGORY
DOT Projects

Florida icon

LEAD AGENCY
Florida

Other Agencies with Actions or Authorizations:

Department of Commerce icon

Department of Commerce, National Oceanic and Atmospheric Administration

Department of Defense icon

Department of Defense, US Army Corps of Engineers - Regulatory

Department of Homeland Security icon

Department of Homeland Security, US Coast Guard

Department of the Interior icon

Department of the Interior, Fish and Wildlife Service

Description:

The proposed project involves replacement of the John T. Brooks Bridge (Bridge Number 570034) which carries S.R. 30 (U.S. 98) over the Santa Rosa Sound which includes the GIWW in Okaloosa County. To accommodate the bridge replacement, intersection improvements are necessary at S.R. 145 (Perry Avenue) on the west end of the bridge in the City of Fort Walton Beach, and in the vicinity of Santa Rosa Boulevard, extending to Pier Road on the east end on Okaloosa Island. 

Permitting Timetable

The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.

  • For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Loading ...
Overall Project Timetable
 
STATUS
Schedule
Extension or Delay
Ahead of Schedule
Paused
No End Date
Planned

Action Information

For additional information, please select an Action from the Permitting Timetable above.

  • Action:  
  • Responsible Agency:  
  • Bureau:  
  • Action Status:  
  • SHPO:  
  • Action Identifier:  
  • Action Outcome:  
Milestone Original Target Date Current Target Date Milestone Complete