Bishopville Truck Route

PROJECT WEBSITE: Bishopville Truck Route

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.

In Progress icon

ENVIRONMENTAL REVIEW AND PERMITTING STATUS
IN PROGRESS

ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
07/30/2021

1 out of 3

ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

Surface Transportation icon

SECTOR
Surface Transportation

CATEGORY
DOT Projects

Department of Transportation icon

LEAD AGENCY
Department of Transportation, Federal Highway Administration

Description:

The FHWA, in cooperation with the South Carolina Department of Transportation (SCDOT) and the Santee-Lynches Regional Council of Governments (SLRCOG), will prepare an Environmental Impact Statement (EIS) on a proposal to provide a truck route in the vicinity of the City of Bishopville in Lee County, South Carolina, from US 15 near I-20, southwest of the City, to the junction of US 15 and Bethune Highway (SC 341), northeast of the City.  The project study area is generally defined by the area bordered by US 15 / I-20 Interchange to the southwest, US 15 just north of Bethune Highway (SC 341) to the northeast, the intersection of Pinchum Sly Road (S-15) and Camden Highway (SC 34) to the northwest and the intersection of Wisacky Highway (SC 341) and Mac Stuckey Lane (local road) to the southeast. US 15 (N. Main Street) through downtown Bishopville is currently a two-lane roadway with a raised median and on-street parking. On average, over 700 large commercial trucks travel through downtown daily. The purpose of the project is to address the existing and future truck traffic traveling through downtown Bishopville.  The EIS for the proposed project will consider the No-build Alternative as well as build alternatives within the identified project study area that would meet the purpose and need of the project. The EIS will promote informed decision making in the development of a solution to address truck traffic through the downtown area.  This EIS will also evaluate options which may enhance the economic development of the area.

Permitting Timetable

The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.

  • For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Loading ...
Overall Project Timetable
 
STATUS
Schedule
Extension or Delay
Ahead of Schedule
Paused
No End Date
Planned

Action Information

For additional information, please select an Action from the Permitting Timetable above.

  • Action:  
  • Responsible Agency:  
  • Bureau:  
  • Action Status:  
  • SHPO:  
  • Action Identifier:  
  • Action Outcome:  
Milestone Original Target Date Current Target Date Milestone Complete