Official US Government Icon

Official websites use .gov
A .gov website belongs to an official government organization in the United States.

Secure Site Icon

Secure .gov websites use HTTPS
A lock ( ) or https:// means you’ve safely connected to the .gov website. Share sensitive information only on official, secure websites.

605/Valley Blvd: Interchange Improvement Project

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.

In Progress icon

ENVIRONMENTAL REVIEW AND PERMITTING STATUS
IN PROGRESS

ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
07/13/2021

1 out of 2

ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

Surface Transportation icon

SECTOR
Surface Transportation

CATEGORY
DOT Projects

California icon

LEAD AGENCY
California, CalTrans

Other Agencies with Actions or Authorizations:

California icon

California

Description:

The California Department of Transportation (Caltrans), in cooperation with Los Angeles County Metropolitan Transportation Authority (LA Metro), San Gabriel Valley Council of Governments (SGVCOG), Gateway Cities Council of Governments (GCCOG), Los Angeles County Department of Public Works (LACDPW), and City of Industry propose to improve mobility and relieve congestion, capacity constraints, and other related deficiencies on Interstate 605 (I-605) at the Valley Boulevard interchange. The I 605/Valley Boulevard Interchange Improvements Project (project) is an Early Action Project (EAP) of the I-605 Corridor Improvement Project and is located approximately two miles north of State Route 60 (SR-60) and a half-mile south of Interstate 10 (I-10) within portions of the City of Industry and unincorporated Los Angeles County.

Project improvements would occur at the I-605 and Valley Boulevard interchange between post miles R19.2 and R19.5, and include improvements to Valley Boulevard, Temple Avenue, the southbound (SB) loop off-ramp and northbound (NB) off-ramp onto Valley Boulevard, and the SB on-ramp, northbound (NB) loop on-ramp, and NB on-ramp from Valley Boulevard onto I-605. The new configuration and improvements would improve ramp queueing, capacity, and enhance motorist, bicycle, and pedestrian safety. 

Permitting Timetable

The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.

  • For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Loading ...
Overall Project Timetable
 
STATUS
Schedule
Extension or Delay
Ahead of Schedule
Paused
No End Date
Planned

Action Information

For additional information, please select an Action from the Permitting Timetable above.

  • Action:  
  • Responsible Agency:  
  • Bureau:  
  • Action Status:  
  • SHPO:  
  • Action Identifier:  
  • Action Outcome:  
Milestone Original Target Date Current Target Date Milestone Complete