Official US Government Icon

Official websites use .gov
A .gov website belongs to an official government organization in the United States.

Secure Site Icon

Secure .gov websites use HTTPS
A lock ( ) or https:// means you’ve safely connected to the .gov website. Share sensitive information only on official, secure websites.

5/56 Missing Connection

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.

Complete icon

ENVIRONMENTAL REVIEW AND PERMITTING STATUS
COMPLETE

COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
09/07/2017

3 out of 3

ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

Surface Transportation icon

SECTOR
Surface Transportation

CATEGORY
DOT Projects

California icon

LEAD AGENCY
California, CalTrans

Other Agencies with Actions or Authorizations:

California icon

California

Department of the Interior icon

Department of the Interior, Fish and Wildlife Service

Description:

A proposed project to address regional mobility between southbound Interstate 5 (I-5) and eastbound State Route 56 (SR 56) and westbound SR 56 and northbound I-5. Alternatives have been developed to be sensitive to the community and environment, while addressing regional connectivity and local congestion.

Permitting Timetable

The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.

  • For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Loading ...
Overall Project Timetable
 
STATUS
Schedule
Extension or Delay
Ahead of Schedule
Paused
No End Date
Planned

Action Information

For additional information, please select an Action from the Permitting Timetable above.

  • Action:  
  • Responsible Agency:  
  • Bureau:  
  • Action Status:  
  • SHPO:  
  • Action Identifier:  
  • Action Outcome:  
Milestone Original Target Date Current Target Date Milestone Complete